Construction Environment & Substrate Preconditions
1. The substrate must be dry. Construction is strictly prohibited on rainy days, before the substrate dries after rain, or when condensation and dampness occur. High humidity tends to clog dust removal pipelines and cause steel shot caking. If the substrate gets damp after shot blasting, the waterproof bonding layer will fail directly.
2. Temperature: Substrate temperature shall generally be ≥ 5℃. Construction is not recommended when wind force reaches Grade 4 or above, as dust will be difficult to collect and steel shot is prone to being blown away.
3. Substrate pre-treatment: Remove oil stains, protrusions, exposed steel bars and thick laitance in advance. Repair pits and cracks first. Oil stains must be thoroughly cleaned; waterproofing membrane cannot adhere well even after shot blasting on oily substrate.
4. Concrete strength: Shot blasting can only be carried out after the concrete reaches the design strength. Early shot blasting is forbidden to prevent loosening of the surface concrete layer.